Bayze Shutdowns International BV
The Netherlands, Breda
  Always in Control with   MYBAYZE                                   for Shutdowns       ©Copyright Bayze 2010-2017
    Shutdown Data
www.Shutdownplaza.com     Company Comp1   Generated x times
  Dutch Brochure         Country Country   Updated x times
 
Apple
    Plant Plant1      
      Sd-Number 2017May      
               
      Goals for each Shutdown to focus on:  
      1- 100% Safety for All    
      2- Within time      
      3- Within Budget      
  Efficiency Is All That Matters®              
Theory Go To Reports  
Shutdown / TA Management Model ScopeIndex General    
Typical TA-Ms Planning - Classic Way Scope ManHour Regional Overall Plan !    
Typical TA Ms Planning Innovative vs Classic Histogram/S-curve      
  Wall Plan      
    MyShutdown    
    Summary Man-hours Equipment Summary    
    Item Man-hours Item Pcs    
    1-Scaffolding 70,10 1-Heat Exchangers 3    
Lifetime Reliability   2-Insulation 43,02 2-Vessels 2    
    3-Cleaning 18,00 3-Columns 0    
    4-Painting 8,00 4-Tanks 0    
    5-Spading 52,80 5-Reactors 0    
    6-Mechanical 322,66 6-Misc.Equipment 0    
    7-Instrumentation 17,60 7-…..      
Your Stuff Library 8-Electrical 13,60 8-……      
    Total -> 545,78 Total -> 5    
         
    Summary Costs    
    Item Man-hours Price/h Costs    
    1-Scaffolding 70,10 40,00 2.804,00    
    2-Insulation 43,02 40,00 1.720,92    
    3-Cleaning 18,00 40,00 720,00    
    4-Painting 8,00 40,00 320,00    
    5-Spading 52,80 35,00 1.848,00    
    6-Mechanical 322,66 50,00 16.133,00    
    7-Instrumentation 17,60 50,00 880,00    
    8-Electrical 13,60 50,00 680,00 Number : 188  
    Total -> 545,78   25.105,92 File Name: MyBayzePlant12017May0.xls  